Route 83 Lift Station

This Project consists of the replacement of as existing sanitary lift station including demolition of various surface amenities including the tops of the existing wet well as well as the associated piping and pumps to 20 feet below grade, replacing with submersible pumps, electronic controls, and piping; tying into the existing Supervisory Control and Data Acquisition (SCADA) system and all other modifications necessary to have a fully operating lift station. The lift station is located south of the intersection of St. Charles Road and Route 83 on the west side of Route 83 near the dead-end of S. Riverside Court in the Village of Villa Park, Illinois.

Bidding Documents


Organization Organization Address 
 Marc Kresmery 1725 Weld Rd.
Elgin, IL 60123
Flow-Technics 181 Ontario St.
Frankfort, IL 60423
Berger Excavating 1205 Garland Rd.
Wauconda, IL 60084
H. Linden & Sons 722 E. South St. Unit D
Plano, IL 60545
 Bolder Contractors 316 Cary Point Dr.
Cary, IL 60013
 Bid Tool 14205 N. Mopac, Ste. 550
Austin, TX 78728
 John Neri Construction Company 770 W. Factory Rd.
Addison, IL 60101
 Landmark Environmental Systems 1813 N. Mill St.
Naperville, IL 60563
 Dimeo Brothers 720 Richard Lane
Elk Grove, IL 60007
 Sheridan Plumbing and Sewer 6754 W. 74th St.
Bedford Park, IL 60638

Project Updates

Posted Date
 March 4, 2016 Project is closed out.
 May 29, 2015 A punch list inspection meeting was held on 05/22/2015. The contractor is now working to complete this punch list work. Staff also processed a pay request this week. 
 May 22, 2015 A punch list inspection is scheduled 05/22/2015.
 May 15, 2015 A punch list inspection is scheduled for next week.
 May 1, 2015 The lift station was started up this week following replacement of the pumps. Some work pertaining to the control and electrical systems still remains. 
 April 10, 2015 Construction for this project is underway. The control cabinet and concrete pad were installed this week, along with most of the electrical conduits. 
 April 3, 2015 Construction for this project is underway. It is expected that work is to be completed prior to 05/01/2015. 
 March 6, 2015 A pre-construction meeting has been held. It is expected that work is to be completed prior to 05/01/2015.
 October 24, 2014 This project was advertised for bidding, today, 10/24/2014. Staff completed preparation of the bid manual for the project this week.