2017 Central Boulevard Improvement Project
General Information
Project Location(s): | Central, Cornell to Villa Myrtle, Kenilworth to Central Cortesi, Kenilworth to Central |
---|---|
Project Status: | Construction Complete |
Bid Opening Date: | March 28, 2017, 10:00 a.m. |
Construction Start Date: | June 12, 2017 |
Construction Completion Date: | October 2017 |
Contractor: | A Lamp Concrete Contractors, Inc. 1900 Wright Boulevard Schaumburg, Illinois 60193 |
Construction Engineer: | Clark Dietz, Inc. |
Design Engineer: | RJN Group, Inc. |
Awarded Contract Amount: | $884,744.75 |
Adjusted Final Contract Amount: | $764,843.80 |
Funding Sources: | Street Improvement Fund (Referendum), Water Supply Fund, Wastewater Fund, Kenilworth TIF Fund |
Objective
To improve the condition of the roadway by means of various pavement rehabilitation methods.
Description
This project consists of the rehabilitation of East Central Boulevard from Cornell Avenue to Villa Avenue and South Myrtle Avenue from Kenilworth Street to Central Boulevard, and Cortesi Avenue from Kenilworth Street to Central Boulevard. The project includes combined sewer separation. Some selective water system and sanitary sewer system improvements are also included.
Justification
The Village's pavement management program has determined that the condition of the street has deteriorated to the point that pavement rehabilitation is needed. This project is to be partially funded by voter approved bond proceeds.
Bidding Documents
Project Updates
Posted Date | Description |
---|---|
September 21, 2017 | Sod installation is complete. Only punch list work remains. |
September 15, 2017 | Sod installation is expected soon and a punch list has been created. |
September 8, 2017 | Striping was installed this week and sod is expected to be installed soon. |
September 1, 2017 | Asphalt surface was installed. All the remains is landscape restoration. |
August 25, 2017 | Concrete work is complete and asphalt binder course has been installed. |
August 18, 2017 | Concrete work began this week. |
August 11, 2017 | Concrete work should begin next week. |
August 4, 2017 | Installation of the water and sewer service for the development at 324 East Central was completed. Concrete work should begin next week. |
July 28, 2017 | Excavation of pavement and curb and gutter on Central is nearly complete. |
July 21, 2017 | Excavation of pavement and curb and gutter continued but was slow due to rain. |
July 14, 2017 | Excavation of pavement and curb and gutter continued but was slow due to rain. |
July 7, 2017 | Excavation of pavement and curb and gutter began this week. |
June 30, 2017 | Underground installation is complete and pavement excavation is expected to begin in the next week. |
June 23, 2017 | Underground installation continues. |
June 16, 2017 | Underground installation continues. |
June 9, 2017 | Construction activities began this week with saw-cutting and some underground installation. |
May 26, 2017 | A pre-construction meeting was held on 05/15/2017. Construction is expected to begin the week of 06/05/2017. |
May 5, 2017 | A pre-construction meeting is scheduled for 05/15/2017. |
April 14, 2017 | A contract was awarded by the Board at the 04/10/2017 Board meeting. Staff is working to execute contracts and schedule a pre-construction meeting. |
April 7, 2017 | A contract will be presented to the Board for consideration at the 04/10/2017 Board meeting. |
March 31, 2017 | A bid opening was held on 03/28/2017 and A Lamp was the apparent low bidder. Staff is working to present a contract to the board for consideration. |
March 17, 2017 | The job was advertised on 03/10/2017 with a bid opening on 03/28/2017. |
March 10, 2017 | Final Plans and Specs have been approved. The job will be advertised on 03/10/2017 with a bid opening on 03/28/2017. |
March 3, 2017 | The consultant has submitted final Plans and Specs and staff is working to complete a final review and get the project out to bid. |
February 24, 2017 | Staff has provided the consultant with comments to the 90% Plans and Specs. |
February 17, 2017 | Staff is in the process of reviewing 90% Plans and Specs for the project. |
February 10, 2017 | Consultant has submitted plans and specs to the Village for review. |
January 20, 2017 | Consultant is working to prepare Phase II Plans and Specs. |
Planholders
Organization | Organization Address |
---|---|
Fox Excavating | 1305 South River Street Batavia, Illinois 60510 |
G&M Cement | 58 West Commercial Addison, Illinois 60101 |
Orange Crush LLC | 321 Center Street Hillside, Illinois 60162 |
Chicagoland Paving | 225 Tesler Road Lake Zurich, Illinois 60047 |
Elanar Construction | 6620 West Belmont Avenue Chicago, Illinois 60634 |
Archon Construction | 563 South Route 53 Addison, Illinois 60101 |
J. Congdon Sewer Services Inc. | 170-A Alexandra Way Carol Stream, Illinois 60188 |
Dimeo Brothers | 720 Richard Lane Elk Grove Village, Illinois 60007 |
K-Five Construction Corporation | 13769 Main Street Lemont, Illinois 60439 |
John Neri Construction Co. | 770 Factory Road Addison, Illinois 60101 |
A Lamp Concrete Contractors | 1900 Wright Boulevard Schaumburg, Illinois 60193 |
Cerniglia Co. | 3421 West Lake Street Melrose Park, Illinois 60160 |
Landmark Contractor Inc. | 11916 West Main Street P.O. Box 1104 Huntley, Illinois 60142 |
J.A. Johnson Paving Co. | 1025 East Addison Court Arlington Heights, Illinois 60005 |
R.W. Dunteman Co. | 600 South Lombard Road Addison, Illinois 60101 |
Alliance Contractors Inc. | 1166 Lake Avenue Woodstock, Illinois 60098 |
Martam Construction | 1200 Gasket Drive Elgin, Illinois 60120 |
V3 Companies | 7325 Janes Avenue Woodridge, Illinois 60517 |
Suburban General Contractors Inc. | 1019 East 31st Street Elgin, Illinois 60526 |
PCE Construction and Engineering | 1000 Independence Boulevard Yorkville, Illinois 60560 |
Contact Us
-
Michael Guerra, P.E.
Public Works Director
Email the Engineering Division
Online Contact Form
Staff Directory
Office Address
Public Works Department
11 West Home Avenue
Villa Park, Illinois 60181
Mailing Address
Public Works Department
20 South Ardmore Avenue
Villa Park, Illinois 60181
Ph: 630-834-8505
Fx: 630-834-8509
Emergency: 630-834-7447
Hours
Monday through Friday
7:30 a.m. to 4:00 p.m.