Maple Area Improvement Project

General Information

Project Location(s):
Various (see map)
Project Status:
Design
Bid Opening Date:
TBD
Construction Start Date:
TBD
Construction Completion Date:
TBD
Contractor:
TBD
Construction Engineer:
TBD
Design Engineer:
Edwin Hancock Engineering Company
Awarded Contract Amount:
TBD
Adjusted Final Contract Amount:
TBD
Funding Source(s):
Street Improvement Fund, GO Bonds, Water Supply Fund, Wastewater Fund, Sewer Separation Fund

Objective

To improve the area of the roadway by removing the existing deteriorated pavement and replacing it with new, structurally sound pavement. To reduce the frequency and severity of flooding and sewer backups by separating the existing combined sewer.

Description

This project consists of the reconstruction of selected areas on East Maple Ave, North Summit Ave, East Oak St, East Pine St, East Division St, and North Myrtle Ave within the Village of Villa Park. The project includes combined sewer separation. Some selective water and sanitary sewer system improvements are also included.

Justification

The Village's pavement management program has determined that the condition of these streets has deteriorated to the point that pavement rehabilitation is needed. This project is to be partially funded by voter approved bond proceeds.

Planholders

Organization
Organization Address
None at this time

Project Updates

Date
Description
March 13, 2020Staff has received preliminary plans. The design engineer is now working to complete pre-final plans and specifications.
February 21, 2020The engineer is working to make necessary revisions to the review comments.
December 13, 2019Staff has reviewed the preliminary design plans submitted by the design engineer and provided the design engineer with review comments.
December 2, 2019The first set of Sewer Service Televising letters have been sent to residents located on or near E Pine St within the project area.
November 22, 2019The design engineer has submitted preliminary design plans. Staff reviewed those plans and provided the design engineer with review comments this week.
November 15, 2019Staff has held a progress meeting with the design engineer. The design engineer has submitted preliminary design plans. Staff is in the process of reviewing those plans and expects to provide the design engineer with review comments in the next one to two weeks.
October 11, 2019The design engineer has submitted preliminary design plans. Staff is in the process of reviewing those plans.
July 11, 2019The design engineer has submitted preliminary design plans. Staff is in the process of reviewing those plans.
June 28, 2019This project is currently under design. Preliminary plans are expected to be submitted for review in the next two weeks.
April 18, 2019This project is currently under design. Staff held a progress meeting with the design consultant this week. Preliminary plans are expected to be submitted for review in June.
December 13, 2018Design of the project is ongoing.
October 5, 2018A letter was sent to residents within the project area notifying them of ongoing survey work for the project.