Charles Avenue Improvement Project

General Information

Project Location(s):
Charles Avenue from St. Charles to Oak
Project Status:
Design
Bid Opening Date:
TBD
Construction Start Date:
TBD
Construction Completion Date:
TBD
Contractor:
TBD
Construction Engineer:
TBD
Design Engineer:
Strand Associates, Inc.
Awarded Contract Amount:
TBD
Adjusted Final Contract Amount:
TBD
Funding Source(s):
GO Bonds, Stormwater Fund, Water Supply Fund, Wastewater Fund, Sewer Separation Fund

Objective

To significantly improve the condition of the roadway by removing the existing deteriorated pavement and replacing it with a new structurally sound pavement. To improve water system capacity and reliability by replacing the existing water main.

Description

This project consists of the reconstruction of North Charles Avenue from St. Charles Road to Oak Street. The project includes combined sewer separation. The project also includes replacement of the existing 4'' water main. Some selective sanitary sewer system improvements are also included.

Justification

The Village's pavement management program has determined that the condition of the street has deteriorated to the point that pavement rehabilitation is needed. This project is to be partially funded by voter approved bond proceeds. The existing 4'' water main has insufficient capacity. The Illinois EPA Public Water Supply Loan Program (PWSLP) is expected to provide loan funding for the water main improvements.

Bidding Documents

Contract Documents

Related Documents

PLANHOLDERS

OrganizationOrganization Address
None at this time

Project Updates

Date
Description
June 28, 2019The design engineer has submitted preliminary design plans. Staff is in the process of reviewing those plans.
June 14, 2019The consultant is expected to submit preliminary design plans within the next week.
June 6, 2019Topographic survey, geotechnical investigation, and sewer main televising have been completed. The consultant is currently working to prepare preliminary design plans.
May 30, 2019Geotechnical investigation, including soil borings and pavement cores, is expected to be completed tomorrow.
May 10, 2019Topographic survey was completed this week. The project is currently under design.
May 3, 2019Topographic survey began this week. Public Works staff located Village utilities in the field.
April 25, 2019Staff held a design engineering kick-off meeting this week. Topographic survey is scheduled to begin next week.
April 18, 2019An engineering services agreement has been approved with Strand Associates for design of this project. Staff is working to schedule a kick-off meeting.