Third Avenue Improvement Project (Holly to Division)
General Information
Project Location(s): | North Third Avenue from Holly Court to Division Street |
---|---|
Project Status: | Complete |
Bid Opening Date: | March 16, 2021, at 11:00 a.m. |
Mandatory Pre Bid Meeting: | March 9, 2021, at 11:00 a.m. |
QuestCDN Number: | 7508467 |
Construction Start Date: | June 2021 |
Construction Completion Date: | December 2021 |
Contractor: | John Neri Construction Company, Inc. |
Construction Engineer: | Edwin Hancock Engineering Co. |
Design Engineer: | Christopher B. Burke Engineering, Ltd. |
Awarded Contract Amount: | $948,907.95 |
Adjusted Final Contract Amount: | $1,046,183.94 |
Funding Source(s): | Street Improvement Fund, Water Supply Fund, Sewer Separation Fund |
Objective
To lessen the frequency and severity of flooding and sewer backups by separating the existing combined sewer.
Description
This project consists of the separation of the existing combined sewer main on North Third Avenue from Holly Court to Division Street.
Justification
The combined sewer separation was identified by the 2015 Comprehensive Flood Plan and Storm Sewer Analysis prepared by Christopher B. Burke Engineering, Ltd. (CBBEL).
Bidding & Planholders Information
Village Projects are typically bid through the online bidding service QuestCDN. A list of plan holders as well as the initial bid tabulation will be available on the project page. For more details on how the Village bidding process works, please visit the Bidding Information page.
BID DEADLINE: MARCH 16, 2021, 11:00 A.M. LOCAL TIME
The Village reserves the right to extend the Bid Deadline from this date and time to accept Bids submitted after the Bid Deadline, as the Village, in its sole discretion, determines is in the best interest of the Village.
NOTICE: Separate proposals for the THIRD AVENUE IMPROVEMENTS will be received electronically by the Village of Villa Park, Illinois, at the website www.questcdn.com (QuestCDN #7508467), until the Bid Deadline. Immediately thereafter, the proposals will be read aloud via Zoom. Notwithstanding the foregoing, the Village reserves the right to defer, postpone, delay, or reschedule the Bid Opening for such time and to such date as the Village, in its sole discretion, determines is in the best interest of the Village. The Bid Opening Zoom Meeting can be accessed using the information below:
https://zoom.us/j/91089393347?pwd=V3RIZzRXWkdaTjhselBpNWJFTjlBUT09
Call-in #: 312-626-6799
Meeting ID: 910 8939 3347 Passcode: 160624
Proposals shall be submitted in accordance with the Bidding Documents prepared by Christopher B. Burke Engineering, Ltd., 9575 W. Higgins Road, Rosemont, IL 60018.
Minority and Women Owned Businesses (MBE/WBE) are encouraged to submit bids on this project. Federal Labor Standards, Prevailing Wage Rates, and Section 3 regulations apply to this Project.
MANDATORY PRE-BID MEETING: A mandatory pre-bid meeting for contractors interested will be held on March 9, 2021 at 11:00 a.m. via Zoom. Village and Consulting engineering staff will be on hand to answer questions regarding interpretations of the project plans and specifications and discuss project scheduling. If required, a project addendum will be prepared based upon questions raised by the bidding community and distributed to all attendees for inclusion within their respective bids. It will be the Village’s decision whether bids are opened from Contractors that do not attend the mandatory pre-bid meeting. The mandatory pre-bid Zoom meeting can accessed using the information below:
https://zoom.us/j/96831944309?pwd=Yk8vUVB0VERaR0pDWlFPQks5Z3F6UT09
Call-in #: 312-626-6799
Meeting ID: 968 3194 4309 Passcode: 925293
Bidding Documents
Contract Documents
Related Documents
- Letter to Residents - Notice 01 (Resident Questionnaire) - Third Avenue (Holly to Division)
- Letter to Residents - Notice 02 (Construction Start-Lead Notice) - Third Avenue (Holly to Division)
- Letter to Residents - Notice 03 (Water Shutoff 01) - Third Avenue (Holly to Division)
- Letter to Residents - Notice 04 (Water Shutoff 02) - Third Avenue (Holly to Division)
- Letter to Residents - Notice 05 (Water Shutoff 03) - Third Avenue (Holly to Division)
- Letter to Residents - Notice 06 (Driveway Access) - Third Avenue (Holly to Division)
Project Updates
Date | Description |
---|---|
December 3, 2021 | The project is now complete. |
October 22, 2021 | Construction is complete. Staff is working to close out the project and the CDBG grant. |
October 1, 2021 | Sodding of parkways was completed this week. The only remaining effort is the completion of punch list work. |
September 24, 2021 | Parkway restoration is expected to be completed in the next few weeks. |
August 27, 2021 | A preliminary layer of asphalt was paved this week. Final asphalt surface paving is expected to take place next week. |
August 20, 2021 | The contractor is continuing the process of removing pavement and preparing the roadway base. The process is nearly complete, and next week the contractor is expected to fine-grade the roadway base and pave a preliminary layer of asphalt. |
August 13, 2021 | The contractor is in the process of removing pavement and preparing the roadway base. Next week the contractor will continue to grade the subbase in preparation for paving. Driveway access may be limited as the contractor grades through driveway locations, but temporary ramps will be placed at each driveway once grading is complete. |
August 6, 2021 | Lining of the sanitary sewer main was completed this week. Construction of sidewalk and curb and gutter is currently in progress. |
July 30, 2021 | Underground utility work is complete. A change order to modify the scope of pavement improvements from resurfacing to reconstruction has been approved. Construction of sidewalk and curb and gutter is currently in progress. |
July 23, 2021 | Installation of the new storm sewer is complete. Water system improvements are currently underway. A change order to modify the scope of pavement improvements from resurfacing to reconstruction has been submitted for consideration at the July 26, 2021 Village Board meeting. |
July 2, 2021 | Several scheduled water shutdowns occurred this week to allow water system improvements to be completed. Work has resumed on the installation of the new storm sewer. |
June 18, 2021 | Work continues on the new storm sewer. |
June 11, 2021 | Construction is underway. Work is currently taking place on the installation of the new storm sewer. |
June 4, 2021 | Construction began this week. The intersection of Third and Division is expected to be closed on Monday, June 7th, to allow for the replacement of a sewer manhole in that intersection. |
May 28, 2021 | Some preliminary construction efforts began this week, including tree removal and the installation of tree protection. |
May 14, 2021 | A construction contract has been awarded. Staff is working to get contracts executed. A pre-construction meeting was held with the Contractor and the DuPage County Community Development Commission. Construction is expected to begin the first week of June 2021. |
April 30, 2021 | A construction contract has been awarded. Staff is now working to get the contracts executed. A pre-construction meeting is scheduled for the week of May 10, 2021. |
April 23, 2021 | Staff has obtained approval of the prospective contractor from DuPage County, as required by the terms of the CDBG grant funding awarded to the project. A recommendation to award a construction contract has been submitted for consideration at the April 26, 2021 Village Board meeting. |
April 9, 2021 | Staff is working to obtain approval of the prospective contractor from DuPage County, as required by the terms of the CDBG grant funding awarded to the project. |
March 19, 2021 | A bid opening was held Tuesday, March 16, at 11:00 A.M. via Zoom. The apparent low bidder was John Neri Construction of Addison, IL with an as-read total of $948,907.95. The Village is reviewing the bid submittals. |
February 19, 2021 | The project was advertised for bidding. |
January 11, 2021 | Questionnaires were distributed to residents within the project area. |
January 1, 2021 | The project is under design. Bidding and construction are expected to take place in 2021. |
Contact Us
-
Michael Guerra, P.E.
Public Works Director
Email the Engineering Division
Online Contact Form
Staff Directory
Office Address
Public Works Department
11 West Home Avenue
Villa Park, Illinois 60181
Mailing Address
Public Works Department
20 South Ardmore Avenue
Villa Park, Illinois 60181
Ph: 630-834-8505
Fx: 630-834-8509
Emergency: 630-834-7447
Hours
Monday through Friday
7:30 a.m. to 4:00 p.m.