- Home
- Government
- Departments
- Public Works Department
- Engineering Division
- Construction Projects
- Completed Projects
- Completed Projects 2022
- 2022 Rebuild IL Resurfacing Project
2022 Rebuild IL Resurfacing Project
General Information
Project Location(s): | Division St - Westmore to Addison Elm St - Westmore to Addison Wisconsin Ave - St. Charles to Division |
---|---|
Project Status: | Closeout |
Bid Opening Date: | September 2, 2022, at 10:00 a.m. CST. |
Mandatory Pre Bid Meeting: | N/A |
QuestCDN Number: | 8271001 |
Construction Start Date: | October 17, 2022 |
Construction Completion Date: | 2022 |
Contractor: | Arrow Road Construction Company |
Construction Engineer: | In-House |
Design Engineer: | TranSystems Corp. |
Awarded Contract Amount: | $371,727.21 |
Adjusted Final Contract Amount: | $342,816.96 |
Funding Source(s): | REBUILD Illinois |
Objective
This project consists of the resurfacing of various streets throughout the village.
Description
This project will consist of a mill and overlay of the above roadways. It also includes any necessary road subgrade patching, structure adjustments or reconstruction, curb ramp improvements to comply with ADA requirements, and all necessary restoration work for these improvements.
Justification
The village's pavement management program has determined that these streets are in need of repair.
Bidding & Planholders Information
Village Projects are typically bid through the online bidding service QuestCDN. A list of plan holders as well as the initial bid tabulation will be available on the project page. For more details on how the Village bidding process works, please visit the Bidding Information page.
Bidding Documents
Contract Documents
Project Updates
Date | Description |
---|---|
December 30, 2022 | A final balancing change order has been approved and all punch list work is complete. |
December 9, 2022 | Staff worked this week to finalize quantities and prepare a final balancing change order for the project. The final change order will be submitted for consideration at an upcoming Village Board meeting. Punch list work is the only site work that remains. Staff is working to perform a final inspection and close out the project. |
November 18, 2022 | Completion of final structure adjustments took place this week. Final asphalt surface paving is expected to be completed next week before the Thanksgiving holiday. |
November 11, 2022 | Completion of pavement patching and paving of a preliminary layer of asphalt, or “leveling binder”, took place this week. |
November 4, 2022 | Work completed this week included marking of pavement patching which is expected to be completed next week. Placement of a preliminary layer of asphalt or “leveling binder” is expected to take place after patching, either next week or the week after. |
October 28, 2022 | Construction continued this week. Work completed this week included the adjustment of curb structures, the pouring of concrete for selective sidewalk and curb and gutter replacement, the temporary removal of frames and lids located within the pavement, and the start of the milling of the existing pavement. Pavement patching is scheduled to take place next week, with placement of a preliminary layer of asphalt or “leveling binder” expected to take place after, either late next week or the week after. |
October 21, 2022 | Staff held a preconstruction meeting for the first of the village’s two expected REBUILD Illinois projects and issued a Notice to Proceed to the contractor. Construction began this week with the removal and replacement of select concrete curbs and sidewalk. The contractor is planning on beginning milling the roadway early next week. |
October 7, 2022 | A contract for the construction of the first of the village’s two expected REBUILD Illinois projects was awarded at the September 12, 2022 Village Board meeting. The contracts have been executed and coordination preconstruction efforts is underway. |
September 2, 2022 | A bid opening was held today for the project. The apparent low bidder was Arrow Road Construction Company, of Elk Grove, IL. Staff is in the process of reviewing the bids and will then make a final determination. |
August 18, 2022 | The project was advertised for bidding. The bid opening date is September 2, 2022, at 10:00 a.m. |
Contact Us
-
Michael Guerra, P.E.
Public Works Director
Email the Engineering Division
Online Contact Form
Staff Directory
Office Address
Public Works Department
11 West Home Avenue
Villa Park, Illinois 60181
Mailing Address
Public Works Department
20 South Ardmore Avenue
Villa Park, Illinois 60181
Ph: 630-834-8505
Fx: 630-834-8509
Emergency: 630-834-7447
Hours
Monday through Friday
7:30 a.m. to 4:00 p.m.