2016 Crack Seal Program

General Information

Project Location(s):Various
Project Status:Completed
Bid Opening Date:March 31, 2016
Start Date:July 28, 2016
Tentative Completion Date:August 23, 2016
Contractor:Denler, Inc.
Construction Engineer:In-House
Design Engineer:N/A
Awarded Contract Amount:$134,437.50
Funding Sources:Street Improvement Fund


Objective

To slow down the deterioration of the Village's asphalt pavements.

Map

Bidding Documents

2016 Crack Seal Program Street List

StreetFromToLength (Feet)
BEVERLY AVE

SUNSET DRTERRACE ST1,511
CHARLES AVE

ST CHARLES RDWILDWOOD ST704
CHATHAM AVE

SUNSET DRTERRACE ST1,475
CORNELL AVE

PARK BLVDMADISON ST3,172
DOUGLAS AVE

SUNSET DRTERRACE ST1,444
ELLSWORTH AVE

SUNSET DRSOUTH END1,314
EUCLID AVE

HIGHLAND AVEWASHINGTON BLVD1,332
EUCLID AVE

ST CHARLES RDWILDWOOD ST812
FULTON AVE

SUNSET DRSOUTH END1,300
HAMILTON AVE

PLYMOUTH STSOUTH END747
HARVARD AVE

DIVISION STELM ST793
HIGHLAND AVE

VILLA AVEIL ROUTE 832,072
HUGO CT

PLYMOUTH STVERMONT ST310
ILLINOIS AVE

KENILWORTH AVECENTRAL BLVD869
ILLINOIS AVE

PARK BLVDMADISON ST3,291
ILLINOIS AVE

ST CHARLES RDWILDWOOD ST648
MADISON ST

SUMMIT AVEEAST END3,320
MONTEREY AVE

WASHINGTON BLVDMADISON ST1,326
OAKLAND AVE

PARK BLVDMADISON ST3,854
OAKLAND AVE

ST CHARLES RDWILDWOOD ST775
PARK BLVD

ADDISON AVEHARVARD AVE1,326
PRINCETON AVE

PARK BLVDMADISON ST2,916
PRINCETON AVE

ELM STST CHARLES RD1,007
RIDGE RD

LINCOLN AVEWESTMORE AVE1,210
SCHOOL ST

WISCONSIN AVEARDMORE AVE2,216
SUMMIT AVE

ST CHARLES RDWILDWOOD ST757
SUNSET DR

LINCOLN AVEWESTMORE AVE1,214
VERMONT ST

HUGO CTWESTMORE AVE407
WILDWOOD ST


ILLINOIS AVEEUCLID AVE1,088

TOTAL: 43,210 Square Feet