2017 Pavement Patching Program
General Information
Project Location(s): | Various (See Map (PDF)) |
---|---|
Project Status: | Completed |
Bid Opening Date: | October 12, 2017, 10:00 a.m. |
Start Date: | November 1, 2017 |
Completion Date: | November 17, 2017 |
Contractor: | J.A. Johnson Paving Company 1025 East Addison Court Arlington Heights, Illinois 60005 |
Construction Engineer: | In-House |
Design Engineer: | In-House |
Awarded Contract Amount: | $169,545.00 |
Adjusted Final Contract Amount | $185,298.30 |
Funding Sources: | Street Improvement Fund |
Objective
To improve the condition of the roadway by milling the existing, deteriorated pavement surface and replacing it with a new pavement surface in select areas.
Bidding Documents
- Specifications (NOT FOR BID) (PDF)
- Proposed Patching Street Map (Bidding Version) (PDF)
- Bid Tabulation (PDF)
Project Documents
Contract Documents
- None at this time
Planholders
Organization | Organization Address |
---|---|
Brothers Asphalt Paving, Inc. | 315 South Stewart Avenue Addison, Illinois 60101 |
A Lamp Concrete Contractors, Inc. | 1900 Wright Boulevard Schaumburg, Illinois 60193 |
Orange Crush, LLC | 321 Center Street Hillside, Illinois 60162 |
J. A. Johnson Paving | 1025 Addison Court Arlington Heights, Illinois 60005 |
Chicagoland Paving Contractors, Inc. | 225 Telser Road Lake Zurich, Illinois 60047 |
Arrow Road Construction | 3401 South Busse Road Mount Prospect, Illinois 60056 |
K-Five Construction Corporation | 13769 Main Street Lemont, Illinois 60439 |
R.W. Dunteman Co. | 600 South Lombard Road Addison, Illinois 60101 |
Schroeder Asphalt Services | P.O. Box 831 Huntley, Illinois 60142 |
Project Updates
Posted Date | Description |
---|---|
November 16, 2017 | All work is complete. Staff is working to close out the project. A final change order is expected to be presented to the Board at a Board Meeting on 12/04/2017. |
November 2, 2017 | Construction began on November 1 and weather permitting will be completed by the end of next week. |
October 27, 2017 | A pre-construction meeting for this project was held today, October 27, 2017. Construction is tentatively scheduled to begin on November 1, 2017, weather permitting. |
October 24, 2017 | A contract for this project was awarded to J. A. Johnson Paving Co. of Arlington Heights, Illinois, in the amount of $169,545.00. Staff is working to execute contracts and set up a pre-construction meeting. |
October 12, 2017 | The Village held a bid opening for this project today, October 12, 2017. The apparent low bidder was J. A. Johnson Paving Co. of Arlington Heights, Illinois, with an as-read bid in the amount of $169,545.00. Staff is now in the process of reviewing bids and checking references. |
September 29, 2017 | This project was advertised for bidding today, September 29, 2017. A bid opening is scheduled for October 12, 2017. |
Contact Us
-
Michael Guerra, P.E.
Public Works Director
Email the Engineering Division
Online Contact Form
Staff Directory
Office Address
Public Works Department
11 West Home Avenue
Villa Park, Illinois 60181
Mailing Address
Public Works Department
20 South Ardmore Avenue
Villa Park, Illinois 60181
Ph: 630-834-8505
Fx: 630-834-8509
Emergency: 630-834-7447
Hours
Monday through Friday
7:30 a.m. to 4:00 p.m.