- Home
- Government
- Departments
- Public Works Department
- Engineering Division
- Construction Projects
- Completed Projects
- Completed Projects 2018
- 2018 ADA Sidewalk Improvement Project
2018 ADA Sidewalk Improvement Project
General Information
Project Location(s): | 14 intersections (see map) |
---|---|
Project Status: | Closeout |
Bid Opening Date: | March 20, 2018, 10:00 a.m. |
Start Date: | May 17, 2018 |
Completion Date: | Fall 2018 (tentative) |
Contractor: | A Lamp Concrete Contractors, Inc. |
Construction Engineer: | In-House |
Design Engineer: | In-House |
Awarded Contract Amount: | $85,220.00 |
Funding Sources: | Capital Projects Fund |
Objective
To significantly improve the condition of related sidewalk ramps by removal of the old material and reconstructing them to the latest ADA standards.
Description
This project consists of the reconstruction of sidewalk ramps intersections located along Lincoln Avenue from Terrace Street to Roy Drive, at Ridge Road and Roy Drive, both ends of Hugo Court, Mission Avenue from Pleasant Avenue to Terrace Street. The replacement of deteriorated curb sections, restoration of the parkway, and the adjustment of existing utility structures are also included.
Justification
The Village has determined that the condition of the ramps has deteriorated to the point that ramp reconstruction is needed to bring them up to the most recent standards. This project is to be fully funded funded by the Capital Projects Fund.
Bidding Documents
Contracts
Project Documents
- Location Map - 2018 ADA Sidewalk Improvement Project (PDF)
- Letter to Residents - Notice 01 - Construction Start (PDF)
Planholders
Organization | Organization Address |
---|---|
Rai Concrete, Inc. | 1827 Blackhawk Dr West Chicago, IL 60185 |
Davis Concrete Construction | 11244 Manhattan Road Monee, IL 60449 |
Lorusso Cement Contractors | 1090 Carolina Dr West Chicago, IL 60185 |
Alliance Contractors, Inc. | 1166 Lake Avenue Woodstock, IL 60098 |
Landmark Contractors, Inc. | 11916 W. Main St PO Box #1104 Huntley, IL 60142 |
A Lamp Concrete Contractors, Inc. | 1900 Wright Boulevard Schaumburg, IL 60193 |
G&M Cement Construction, Inc. | 58 W Commercial Road Addison, IL 60101 |
Schroder & Schroder, Inc. | 7306 Central Park Avenue Skokie, IL 60076 |
Project Updates
Posted Date | Description |
---|---|
October 25, 2018 | A final balancing change order was approved by the Board on October 22, 2018 and staff is working to close out the project. |
October 11, 2018 | A final balancing change order will be presented to the Board for consideration at the October 22, 2018 Board Meeting. |
September 20, 2018 | Sod restoration is complete. The Village is waiting for it to establish before closing out the project. |
September 13, 2018 | Sod restoration is expected to begin next week. |
September 6, 2018 | Staff is working to get a schedule to complete the sod restoration. |
June 14, 2018 | Landscape work has been delayed until Fall due to the forecasted high temperatures. Residents have been notified. |
June 7, 2018 | Landscape work will be completed when weather permits. |
June 1, 2018 | All concrete work is complete. Landscape work will be completed when weather permits. |
May 24, 2018 | The concrete curb has been framed and pouring has begun. The sidewalk is expected to be framed and poured next week. |
May 17, 2018 | Construction removal has been completed. Installation of the new sidewalk is expected the week of May 21, 2018. |
May 10, 2018 | Construction is expected to begin next week with concrete removal. |
May 3, 2018 | A pre-construction meeting was held on May 1, 2018. Construction is expected to start in the next couple of weeks. |
April 16, 2018 | Staff is working to execute contracts and schedule a pre-construction meeting. |
March 22, 2018 | An award recommendation will be presented to the Board for consideration at the April 9, 2018 Board Meeting. |
March 20, 2018 | Project bid submittals were opened on the 19th. The apparent low bidder is A Lamp Concrete Contractors, Inc. |
March 2, 2018 | Project is out to bid. Bid submittals will be opened at 10:00 A.M. on Tuesday, March 20th. |
Contact Us
-
Michael Guerra, P.E.
Public Works Director
Email the Engineering Division
Online Contact Form
Staff Directory
Office Address
Public Works Department
11 West Home Avenue
Villa Park, Illinois 60181
Mailing Address
Public Works Department
20 South Ardmore Avenue
Villa Park, Illinois 60181
Ph: 630-834-8505
Fx: 630-834-8509
Emergency: 630-834-7447
Hours
Monday through Friday
7:30 a.m. to 4:00 p.m.