2018 Pavement Patching Program
General Information
Project Location(s): | Various (see map) |
---|---|
Project Status: | Complete |
Bid Opening Date: | Tuesday, September 11, 2018, at 10:00 a.m. |
Construction Start Date: | October 29, 2018 |
Construction Completion Date: | Spring 2019 |
Contractor: | A Lamp Concrete Contractors, Inc. |
Construction Engineer: | In-House |
Design Engineer: | In-House |
Awarded Contract Amount: | $198,800.00 |
Adjusted Final Contract Amount: | $194,213.35 |
Funding Source(s): | Street Improvement Fund |
Objective
To improve the area of the roadway by removing the existing deteriorated pavement surface and replacing it with a new pavement surface in selected areas.
Description
This project consists of selective resurfacing of roadway areas that have deteriorated over time and use.
Justification
Village engineers have determined that the selected roadway areas have deteriorated to the point that they require maintenance.
Bidding Documents
Contract Documents
Related Documents
PLANHOLDERS
Organization | Organization Address |
---|---|
Meyer Paving, Inc. | 50W363 Rte. 64 Maple Park, IL 60151 |
A Lamp Concrete Contractors, Inc. | 1900 Wright Blvd Schaumburg, IL 60193 |
Construction Management Corp of America | 5106 Walnut Ave Downers Grove, IL 60515 |
Arrow Road Construction | 3401 South Busse Rd Mt. Prospect, IL 60056 |
R.W. Dunteman Co. | P.O. Box 1129, 600 South Lombard Rd Addison, IL 60101 |
Chicagoland Paving, Inc. | 225 Telser Rd Lake Zurich, IL 60047 |
Orange Crush, LLC | 321 Center St Hillside, IL 60162 |
Brothers Asphalt Paving, Inc. | 315 South Stewart Ave Addison, IL 60101 |
K-Five Construction Corporation | 999 Oakmont Plaza Dr, Suite 200 Westmont, IL 60559 |
J.A. Johnson Paving Company | 1025 East Addison Ct Arlington Heights, IL 60005 |
Project Updates
Date | Description |
---|---|
August 30, 2019 | All work is complete. A final balancing change order has been approved and staff has processed final payment to the contractor. This project is now closed. |
August 15, 2019 | All work is complete. Staff has submitted a proposed final balancing change order for Village Board consideration. |
July 18, 2019 | All work is complete and staff has processed final payment. A final balancing change order is expected to be submitted to the Village Board for consideration. |
July 3, 2019 | All patching is complete. Staff is working with the contractor to close out the contract. |
June 14, 2019 | Surface patches (2'') are complete. Work on the full-depth patches is pending. |
May 30, 2019 | Construction started this week. Work is expected to last one to two weeks. |
May 23, 2019 | Construction is expected to start the week of May 27, 2019. Staff is preparing for construction start. |
May 16, 2019 | Construction is tentatively expected to start the week of May 20, 2019. Staff is preparing for construction start. |
May 10, 2019 | Construction is expected to start the week of May 20, 2019. |
April 18, 2019 | Staff is working with the contractor to coordinate the start of work. |
March 14, 2019 | Work will begin after the asphalt plants open for the season. |
November 22, 2018 | Construction has been put on hold due to the early winter weather and the closing of asphalt plants. |
September 27, 2018 | A contract with A Lamp has been approved. Staff will schedule a preconstruction meeting and construction start date. |
September 13, 2018 | A bid opening was held on September 11, 2018. A Lamp Concrete Contractors, Inc. is the apparent low bidder. |
Contact Us
-
Michael Guerra, P.E.
Public Works Director
Email the Engineering Division
Online Contact Form
Staff Directory
Office Address
Public Works Department
11 West Home Avenue
Villa Park, Illinois 60181
Mailing Address
Public Works Department
20 South Ardmore Avenue
Villa Park, Illinois 60181
Ph: 630-834-8505
Fx: 630-834-8509
Emergency: 630-834-7447
Hours
Monday through Friday
7:30 a.m. to 4:00 p.m.