- Home
- Government
- Departments
- Public Works Department
- Engineering Division
- Construction Projects
- Active Projects
- 2019 Sewer Rehabilitation Program
2019 Sewer Rehabilitation Program
General Information
Project Location(s): | Various |
---|---|
Project Status: | Contract Execution |
Pre-Bid Meeting Date: | July 11, 2019, at 10:00 a.m. |
Bid Opening Date: | July 30, 2019, at 11:00 a.m. |
Construction Start Date: | February 2020 |
Construction Completion Date: | Spring 2020 |
Contractor: | Michels Corporation |
Construction Engineer: | RJN Group, Inc. |
Design Engineer: | RJN Group, Inc. |
Awarded Contract Amount: | $1,156,040.70 |
Adjusted Final Contract Amount: | TBD |
Funding Source(s): | IEPA Loan |
Objective
To significantly improve the condition of selected sanitary sewer mains throughout the Village.
Description
The 2019 Sewer Rehabilitation Program consists of the rehabilitation of 30 manholes, 22,000 linear feet of sewer lining with diameter ranging between 8” and 21”, grouting of 100 laterals, installation of 2 T-liners and 1 new service lateral, 4 point repairs, restoration, and other related and incidental work.
Justification
The Village has identified areas of the sewer network that are in need of rehabilitation. The rehabilitation efforts will reduce the inflow and infiltration (I/I) of both stormwater and debris into the sanitary sewer system, thus lessening both the frequency and severity of sewer surcharges and sewer backups. The life of the existing sewer will also be extended.
The manholes, lining, grouting, point repairs, and related work for the 2019 Sewer Rehabilitation Program were financed by the Water Pollution Control Loan Program (WPCLP) State Revolving Fund (SRF). The SRF program is administered by the Illinois Environmental Protection Agency and receives a portion of its money to fund these types of projects from the U.S. Environmental Protection Agency. This project includes areas throughout the Village of Villa Park. Once complete, it will improve water quality for area residents and businesses in Villa Park and the Salt Creek Watershed by reducing the inflow and infiltration (I/I) of both stormwater and debris into the sanitary sewer system, thus lessening both the frequency and severity of sewer surcharges and sewer backup. SRF programs operate in each state to provide communities the resources necessary to build, maintain, and improve the infrastructure that protects one of our most valuable resources: water.
BIDDING Information
The Bidding Documents are on file for inspection at the office of the Village of Villa Park Public Works Department, 11 West Home Avenue, Villa Park, Illinois, 60181. Digital copies of the bid documents are available at www.questcdn.com for a non-refundable fee of $30.00. These documents may be downloaded by entering Quest Project Number 6396570 on www.questcdn.com.
Bidding Documents
Contract Documents
Related Documents
PLANHOLDERS
Organization | Organization Address |
---|---|
See project page on QuestCDN |
Project Updates
Date | Description |
---|---|
January 1, 2021 | All work that was a part of the original contract is now complete. The three additional point repairs approved by Change Order #3 have also been completed. Remaining work added by Change Order #2 is expected to resume in the next month. |
December 4, 2020 | The contractor is in the process of completing remaining sewer lining work that was added by Change Order #2. |
November 13, 2020 | All work that was a part of the original contract is now complete. The three additional point repairs approved by Change Order #3 have also been completed. The contractor is now in the process of completing remaining sewer lining work that was added by Change Order #2. |
November 6, 2020 | Michels has started the final work for the final change order with the point repair on Hugo St. |
October 30, 2020 | All work that was a part of the original contract is now complete. It has been determined that some of the sewer lining added as a part of Change Order #2 will no longer be sufficient by itself, and that point repairs at three locations will be necessary before that lining can take place. The Board approved the change order for the completion of these additional point repairs at the October 26, 2020 Village Board meeting. Staff is coordinating the remaining work with the contactor. |
October 23, 2020 | All work that was a part of the original contract is now complete. It has been determined that some of the sewer lining added as a part of Change Order #2 will no longer be sufficient by itself, and that point repairs at three locations will be necessary before that lining can take place. Staff has submitted a change order for the completion of these additional point repairs for consideration at the 10/26/2020 Village Board meeting. |
October 9, 2020 | The alternate work that was approved by change order is currently in progress. Some additional point repairs have been identified during the completion of this alternate work. Staff plans to submit a change order for the completion of these additional point repairs for consideration by the Village Board at an upcoming board meeting. |
September 11, 2020 | All work that was a part of the original contract is now complete and documentation is being reviewed. The alternate work that was approved by change order is currently in progress. Staff is working with the construction engineer to finalize the remaining improvements, with a focus on rehabilitation of sewers on North Westmore Avenue. It is anticipated this work being completed by next month. |
September 4, 2020 | It is anticipated that the remaining work will be completed by next month. |
August 14, 2020 | All work that was a part of the original contract is now complete. The alternate work that was approved by change order is currently in progress. Staff is working with the construction engineer to identify the scope of remaining improvements, with a focus on rehabilitation of sewers on North Westmore Avenue. |
July 24, 2020 | The alternate work is still in progress. |
July 17, 2020 | All work that was a part of the original contract is now complete. The alternate work that was approved by change order is currently in progress. Staff is working with the construction engineer to identify the scope of remaining improvements with a focus on rehabilitation of sewers on North Westmore Avenue. |
July 3, 2020 | Lining work and manhole rehabilitation are in progress. Staff is working with the construction engineer to identify the scope of remaining improvements with a focus on rehabilitation of Westmore Ave. |
June 26, 2020 | Lining work and manhole rehabilitation are in progress. Staff is working with the construction engineer to identify the scope of remaining improvements. |
June 19, 2020 | Point repair work is complete. Lining work and manhole rehabilitation are in progress. |
June 12, 2020 | Lining work is in progress. |
May 22, 2020 | Point repair work is complete. Lining work is in progress. Two change orders were approved at the May 18, 2020 board meeting. |
May 15, 2020 | Point repair work is complete. Lining work is in progress. Staff has submitted two change orders for consideration at the May 18, 2020 board meeting. |
May 8, 2020 | Lining and point repair work is in progress. |
May 1, 2020 | Construction is underway. Lining and point repair work are in progress. The heavy rain over the last few days has slowed lining efforts. |
April 24, 2020 | Construction is underway. Lining and point repair work are in progress. |
April 17, 2020 | Construction is underway. Lining and point repair work began this week. |
April 10, 2020 | Construction is underway. Lining and point repair work is expected to begin next week. |
March 27, 2020 | Construction is underway. Flushing, cleaning, and televising of sewers is still in progress. Lining work is expected to begin next week. |
March 13, 2020 | Construction is underway. Flushing, cleaning, and televising of sewers is still in progress. Lining work is expected to begin next week. |
February 21, 2020 | Current efforts include flushing, cleaning, and televising of sewers to be lined. |
February 14, 2020 | Current efforts include flushing, cleaning, and televising of sewers to be lined. Work was on hold at the end of this week due to the cold temperatures. |
February 7, 2020 | Construction began this week. Initial efforts include flushing, cleaning, and televising of sewer mains that are to be lined. |
January 31, 2020 | Construction is expected to begin next week. Initial efforts will include flushing, cleaning, and televising of sewer mains that are to be lined. |
January 24, 2020 | Construction is expected to begin in the next few weeks. Initial efforts will include flushing, cleaning, and televising of sewer mains that are to be lined. |
January 17 ,2020 | Construction of this project is expected to begin next week. Initial efforts will include flushing, cleaning, and televising of sewer mains that are to be lined. |
January 10, 2020 | Construction of this project is expected to begin next week. Initial efforts will include flushing, cleaning, and televising of sewer mains that are to be lined. |
December 27, 2019 | Contracts with Michels Corporation have been executed. Staff is working to coordinate the start of construction. |
November 29, 2019 | Contracts with Michels Corporation are currently pending execution. |
November 22, 2019 | A loan agreement has been executed. A pre-construction meeting has been held. Staff is working to execute contracts with Michels Corporation. |
November 15, 2019 | A pre-construction meeting was held this week. Staff is working to execute contracts with Michels Corporation. |
November 8, 2019 | A loan agreement has been executed. A pre-construction meeting is scheduled for next week. Staff is working to execute contracts with Michels Corporation. |
November 1, 2019 | The Illinois EPA has approved the loan funding for this project and a loan agreement was executed this week. Staff is now working to execute contracts with approved contractor Michels Corporation. |
October 11, 2019 | A bid opening for this project was held on July 30, 2019. A conditional contract award with Michels Corporation has been approved. The contract award is now pending review and approval by the Illinois EPA. |
August 30, 2019 | A conditional contract award with Michels Corporation has been approved. The contract award must now be reviewed and approved by the Illinois EPA. |
August 15, 2019 | A bid opening for this project was held on July 30, 2019. Staff has submitted a recommendation to award a contract to apparent low bidder Michels Corporation. Pending Village Board consideration, the contract award with also need to be reviewed and approved by the Illinois EPA. |
August 2, 2019 | A bid opening was held on July 30, 2019. Staff is in the process of reviewing the bids. |
July 11, 2019 | This project is currently out to bid. A pre-bid meeting was held this week on July 11, 2019. A bid opening is scheduled for July 30, 2019. |
June 28, 2019 | The project is currently out to bid. A bid opening is scheduled for July 30, 2019. |
Contact Us
-
Michael Guerra, P.E.
Public Works Director
Email the Engineering Division
Online Contact Form
Staff Directory
Office Address
Public Works Department
11 West Home Avenue
Villa Park, Illinois 60181
Mailing Address
Public Works Department
20 South Ardmore Avenue
Villa Park, Illinois 60181
Ph: 630-834-8505
Fx: 630-834-8509
Emergency: 630-834-7447
Hours
Monday through Friday
7:30 a.m. to 4:00 p.m.