Project Location(s): | Villa Park Public Works Department, 11 W Home Ave |
---|---|
Project Status: | Closeout |
Bid Opening Date: | Tuesday, June 2, 2020 |
Optional Pre-Bid Meeting: | Thursday, May 19, 2020 |
QuestCDN Number: | 7076836 |
Construction Start Date: | October 12, 2020 |
Construction Completion Date: | 2020 |
Contractor: | Era-Valdivia Contractors, Inc. |
Construction Engineer: | In-House |
Design Engineer: | In-House |
Awarded Contract Amount: | $782,520.00 |
Adjusted Final Contract Amount: | TBD |
Funding Source(s): |
To increase the lifespan of the water tower located on Home Avenue, next to Public Works.
This project consists of the painting of one (1) 500,000 gallon elevated water storage tank located at 11 West Home Avenue, approximately 500 feet west of the intersection of Home Avenue and Ardmore Avenue, in the Village of Villa Park, Illinois. The scope of work includes interior painting, exterior painting, letting, containment and disposal, and other related work. The project also includes several alternate bid items.
The Village has determined that painting and other tower maintenance is needed.
Separate, sealed proposals for the HOME AVENUE WATER STORAGE TANK PAINTING PROJECT project will be received through QuestCDN, until the Bid Deadline. Immediately thereafter, the proposals will be publicly opened and read aloud via Zoom. Notwithstanding the foregoing, the Village reserves the right to defer, postpone, delay, or reschedule the Bid Opening for such time and to such date as the Village, in its sole discretion, determines is in the best interest of the Village.
Date | Description |
---|---|
December 4, 2020 | Tower painting is complete. Project is on closeout. |
October 5, 2020 | A pre-construction meeting was held with the contractor today. Work is expected to begin Monday, October 12, 2020. Cell carriers have previously relocated their antennas to temporary towers located next to the water tower. |